Welcome to our new web site!
To give our readers a chance to experience all that our new website has to offer, we have made all content freely avaiable, through October 1, 2018.
During this time, print and digital subscribers will not need to log in to view our stories or e-editions.
The Howard County Courthouse is getting new insulation. Installation began last week, and phase one is expected to be complete by mid-November.
Phase one includes the main floor of the 1888 …
This item is available in full to subscribers.
We have recently launched a new and improved website. To continue reading, you will need to either log into your subscriber account, or purchase a new subscription.
If you had a login with the previous version of our e-edition, then you already have a login here. You just need to reset your password by clicking here.
If you are a current print subscriber, you can set up a free website account by clicking here.
Otherwise, click here to view your options for subscribing.
Please log in to continue |
|
The Howard County Courthouse is getting new insulation. Installation began last week, and phase one is expected to be complete by mid-November.
Phase one includes the main floor of the 1888 building and water loop. Butzer Mechanical of Jefferson City is the general contractor for the project.
The cost for the first phase will range from $60,000 to $70,000. Phase two, which will include the basement and fresh air intake, is estimated to cost significantly more. No local tax dollars are being spent. The entire project will be paid for with the county’s remaining American Rescue Plan Act (ARPA) funds, commissioners say.